Nathan Dam and Pipelines

Project Summary

The Nathan Dam and Pipelines Project is a major initiative aimed at providing long-term, reliable water supplies to mining, power, urban and agricultural customers in the Surat Coal Basin and the Dawson-Callide sub-region of Central Queensland.

 

Preliminary Works and Feasibility Investigations
Initial advice statement published Early 2008
Nathan Dam draft ToR for the Environmental Impact Statement (EIS) released 13 Sept 2008
Nathan Dam draft ToR submission period closed 17 Oct 2008
Nathan Dam ToR published 13 Feb 2009
Nathan Dam EIS completed and approved by the C-G for consultation Early 2012
Nathan Dam Supplementary EIS completed (if required) Mid 2012
Coordinator-General's report Late 2012
Federal Minister's decision Late 2012
Business case completed Early 2012
If the project is approved:
Detailed design completed 2014
Construction commences 2015
Construction/commissioning completed 2018 *

 

* Timing dependent on foundation customer commitment.