Connors River Dam and Pipelines
Project Summary
This project aims to develop a new water storage in the Connors Isaac sub-catchment of central Queensland to increase the Bowen Basin and surrounding regions' water supply reliability and security.
| Preliminary Works and Feasibility Investigations |
- Preliminary, scoping and feasibility works undertaken
|
Completed
(Late 2007)
|
|
|
Completed
(February 2008)
|
- Concept design engineering undertaken
- Preliminary yield and demand assessments undertaken
|
Completed
(December 2008)
|
| Preliminary Business Case Assessment and EIS preparation |
- Preliminary environmental and cultural heritage assessments
- Geotechnical investigations conducted
- Preliminary design engineering undertaken
- SunWater prepared a preliminary business case to determine the feasibility of the project and secure on-going funding of the project through to final business case stage
- Ongoing consultation and communication with relevant project stakeholders
|
Completed
(December 2009)
|
|
|
Completed
(March 2010)
|
| Final Business Case Assessment |
- SunWater finalised a detailed business case including preliminary designs, refined CAPEX and OPEX estimates, assessed financial and economic benefits and costs of the project, detailed demand assessments including market soundings and commitments, a detailed capital management strategy, detailed risk assessments and assessments of optimum delivery and procurement methods
|
Completed
(December 2010)
|
- The business case was submitted to SunWater’s Shareholding Ministers for assessment and approval
|
Completed
(February 2011) |
| EIS and Approvals |
- The Coordinator-General reviewed all comments made from the EIS public release period and requested further information about the project through a Supplementary Report to the EIS
- SunWater conducted further required investigation/assessment and finalised a Supplementary Report to the EIS
|
Completed
(March 2011)
|
- The Coordinator-General reviews the Supplementary Report, liaises with relevant Advisory Agencies and develops the Coordinator-General’s Report
|
Completed (January 2012)
|
- Federal Minister for the Environment reviews the Coordinator-General’s Report (and other relevant material) under the bilateral agreement and makes a decision on the project
|
Underway
(Expected completion in early 2012) |
- SunWater and preferred tenderers jointly apply for State and local government approvals, as specified in the EIS
|
Underway
(Expected completion in early 2012) |
| Pre-Construction Phase and Customer Agreements |
- SunWater selects construction partners, progresses detailed designs and constructability assessments under a competitive early tenderer involvement (ETI) procurement process
- Further on-site investigations are undertaken to inform detailed design process (geotechnical and engineering assessments)
- SunWater develops agreed construction cost estimates with preferred constructors
- Water Supply and Transport Agreements are negotiated and finalised with potential customers of the project
- Property acquisition, tenure and native title arrangements are finalised
|
Underway
(Expected completion in early 2012) |
| Construction and Commissioning |
- SunWater gains required approvals and permits to commence construction
- Construction proceeds over a period of approximately 2.5 years
- Commissioning of the project is forecast to occur in early 2014
|
Future Stage
(early 2012 to early 2014) |